Revenue System Modernisation

Crown Dependency Government Department

Isle of ManFeatured

Impact

Department now leads its own technology programmes without external PMO support

Duration

18 months

The Challenge

A Crown Dependency revenue department was operating a 25-year-old mainframe system that couldn't support modern tax policy requirements. Previous attempts to replace it had failed, costing £3M with nothing to show.

The department had no internal programme management capability, limited technology expertise, and a history of troubled IT projects. Leadership was understandably skeptical of consultants.

Key constraints:

  • Small internal IT team (6 people)
  • Limited budget (£8M over 3 years)
  • Political pressure for visible progress
  • Data sovereignty requirements preventing standard cloud solutions
  • Procurement thresholds requiring competitive process

Our Approach

We started with a 6-week assessment to understand whether the programme was viable:

Phase 1: Strategic Foundation (Weeks 1-6)

  • Technology options analysis (cloud, hybrid, on-premise)
  • Benefits case validation (did the numbers actually stack up?)
  • Procurement strategy development
  • Internal capability assessment
  • Risk analysis and mitigation planning

Honest finding: The original business case was optimistic. We helped reframe it with realistic timescales and costs.

Phase 2: Procurement Excellence (Months 2-6)

  • Developed clear, testable requirements
  • Ran competitive procurement process
  • Negotiated contract terms preventing vendor lock-in
  • Saved £2.1M through commercial strategy
  • Built internal commercial capability

Key intervention: Challenged vendor pricing assumptions and contractual terms that would have created long-term dependency.

Phase 3: Embedded PMO with Capability Transfer (Months 7-18)

  • Established programme governance and controls
  • Worked alongside internal team, not for them
  • Documented all processes and decisions
  • Trained 4 internal staff in programme management
  • Gradual handover as internal capability grew

The Lumina difference: We started with 4 consultants, scaled to 2, then to 1, then to zero. Each reduction marked capability transferred, not cost-cutting.

The Outcomes

Programme Delivery

  • ✅ Cloud platform delivered on time (Month 18)
  • ✅ On budget (£7.9M vs £8M approved)
  • ✅ All critical requirements met
  • ✅ Data sovereignty maintained
  • ✅ Zero post-launch critical defects

Capability Transfer

  • ✅ Internal PMO now managing Phase 2 independently
  • ✅ 4 staff trained to programme management practitioner level
  • ✅ Documented PMO processes in use across department
  • ✅ Internal team leading vendor management
  • ✅ Department requested zero Lumina involvement in Phase 2

Benefits Realization

  • ✅ 90% of benefits case realized within 12 months
  • ✅ Tax policy changes implemented that were previously impossible
  • ✅ Processing time reduced from 6 weeks to 2 days
  • ✅ Staff productivity gains of 40%

Client Perspective

"Previous consultants left us with documents we couldn't use and decisions we didn't understand. Lumina left us with a team that can run programmes ourselves. The difference was night and day."

— Programme Director

What Made It Work

  1. Honest assessment upfront - We challenged the original business case rather than taking the money
  2. Commercial expertise - Saved £2.1M through smart procurement
  3. Capability transfer from day one - Not a handover activity, a continuous process
  4. Scaled down as capability grew - From 4 consultants to zero over 18 months
  5. Measured our success by their independence - They don't need us for Phase 2

Services Delivered

Lessons Learned

What we'd do again:

  • Honest upfront assessment saved time and money
  • Paired delivery (consultant + internal staff) accelerated capability transfer
  • Documented everything in plain language

What we'd do differently:

  • Start capability transfer even earlier
  • Push harder on benefits measurement framework from day one

Case Study Details

Jurisdiction

Isle of Man

Completed

2023-Q3

Team Size

2-4 consultants (scaled down over time)

Services Delivered

Strategic Consultancy
Technology Strategy
PMO-as-a-Service

Key Outcomes

  • Cloud-based revenue platform delivered on time and budget
  • Internal PMO team now managing Phase 2 independently
  • £2.1M saved through optimized procurement strategy
  • 90% of original benefits case realized within 12 months

Discuss your challenge

Let's talk about your transformation needs.

Get in touch